Project Scope Construction of 92,776 square foot correctional facility to house 173 inmates. This project is to be performed under an accelerated schedule is scheduled to be operational in 16 months.
Mechanical System consisted of a full scale boiler plant, with hot water baseboard, and air handling units. The air side system consisted of multiple air handling units, a full variable air volume system and an air conditioned facility.
Project Team ABM Mechanical, Inc. – Performed all the mechanical contract requirements. Sheridan Corporation – Performed the general contractor responsibilities. Bangor Roofing & Sheet Metal – Performed the sheet metal and breeching fabrication and labor. Mechanical Insulation – Provided insulation services. Trane Controls – Performed automatic temperature control services.